Identification

UMIS Number BG16RFOP002-6.002-0731-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 126705405 BULTEM Ltd.
Funding ERDF ==> Innovations and Competitiveness
Date of the Contract/Order 21.09.2022
Start Date 21.09.2022
End Date 26.07.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Хасково (BG422), Хасково, гр.Хасково

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: "ASO 74" Ltd., Contracted Amount*: 18 620.00 , Reported Amount**: 37 240.00
  • Contractor: IVD Engineering Ltd., Contracted Amount*: 34 050.00 , Reported Amount**: 68 100.00
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 105 340.00 BGN
Grant 52 670.00 BGN
Self amount 52 670.00 BGN
Total actual amounts paid 52 670.00 BGN
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Избор на изпълнител за доставка, монтаж и въвеждане в експлоатация на ДМА - Автоматизирана система за мониторинг на енергопотреблението - 1 брой, състояща се от 19 точки на мерене на електрическа енергия и 1 брой софтуерна платформа за натрупване и анализ на данни., Estimated Amount: 37 375.00
  • Differentiated position 1: Избор на изпълнител за доставка, монтаж и въвеждане в експлоатация на ДМА - Автоматизирана система за мониторинг на енергопотреблението - 1 брой, състояща се от 19 точки на мерене на електрическа енергия и 1 брой софтуерна платформа за натрупване и анализ на данни.
    Contractor: "ASO 74" Ltd.
    Contract total funded value: 18 620.00
Procedure 2 Subject to due process: Избор на изпълнител за доставка, монтаж и въвеждане в експлоатация на ДМА - Компресор за сгъстен въздух с инверторно управление с изсушител - 1 брой, Estimated Amount: 68 310.00
  • Differentiated position 1: Избор на изпълнител за доставка, монтаж и въвеждане в експлоатация на ДМА - Компресор за сгъстен въздух с инверторно управление с изсушител - 1 брой
    Contractor: IVD Engineering Ltd.
    Contract total funded value: 34 050.00

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN