| UMIS Number | BG16M1OP001-5.002-0009-C01 |
| Project Name | "Verification of project expenditure with beneficiary Managing Authority of OP "Transport" 2007-2013 and OP "Transport and Transport Infrastructure" 2014-2020 " |
| Beneficiary | 000695388 Coordination of Programmes and Projects Directorate-Managing Authority of Operational Programme Transport and Transport Infrastructure, Ministry of Transport, Information Technology and Communications |
| Funding | ERDF ==> Transport and Transport Infrastructure 2014-2020 |
| Date of the Contract/Order | 22.07.2019 |
| Start Date | 22.07.2019 |
| End Date | 10.05.2024 |
| Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
| Location of Performance |
|
| Brief description |
Дейността по проекта включва верификация на разходите, докладвани в искания за междинни и окончателни плащания по проекти, финансирани по приоритетна ос „Техническа помощ” на Оперативна програма „Транспорт" 2007-2013 г (ОПТ) и Оперативна програма „Транспорт и транспортна инфраструктура” 2014 – 2020 г. (ОПТТИ), в случаите, при които Управляващият орган (УО) е бенефициент по тях, както следва: - контролни проверки на включените в пакета отчетни документи по проекта, попадащи в искането за плащане и попълване на съответните контролни листове; - проверки на място по проектите по време на изпълнението на проекта или след приключване на дейностите по него, но преди одобрението на окончателното искане за плащане. При одобрение на окончателното искане за плащане задължително се извършва проверка на място; - 100 % документална проверка на цялата документация, свързана с извършените разходи; - изготвяне на доклади за извършена верификация на разходи в междинни и окончателни искания за плащания и за извършена проверка на място; -преглед и одобрение на авансови плащания по проекти, финансирани по приоритетна ос „Техническа помощ” на ОПТ и ОПТТИ, в случаите, при които УО е бенефициент по тях. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Изготвени анализи, доклади и становища, свързани с изпълнението на проекта, Measure Unit: Number, Base Value: 0.00 , Target amount: 127.00 , Reached amount: 102.00 |
| Total Project cost | 24 316.47 EUR |
| Grant | 24 316.47 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 24 316.47 EUR |
| Percentage of EU co-financing | 85.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Избор на консултант осъществяващ дейности по верификация на разходите по проекти с бенефициент Управляващият орган на Оперативна програма „Транспорт и транспортна инфраструктура“ 2014-2020 г.,
Estimated Amount: 13 927.59
|
| Procedure 2 |
Subject to due process: Избор на консултант, осъществяващ дейности по верификация на разходите по проекти, с бенефициент Управляващият орган, които се финансират по Оперативна програма „Транспорт и транспортна инфраструктура“ 2014-2020 г. и Програма "Транспортна свързаност" 2021-2027 г. ,
Estimated Amount: 17 895.22
|
| Procedure 3 |
Subject to due process: Избор на независим консултант за осъществяване на дейности по верификация на разходите по проекти, с бенефициент Управляващият орган, които се финансират по приоритетна ос "Техническа помощ " на Оперативна програма "Транспорт" 2007-2013 г. и Оперативна програма „Транспорт и транспортна инфраструктура“ 2014-2020 г.,
Estimated Amount: 5 816.46
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN