Identification

UMIS Number BG05M2OP001-4.001-0001-C03
Project Name Funding salaries, bonuses and supplementary health insurance for employees working in the Managing Authority of Operational Programme "Science and Education for Smart Growth"
Beneficiary 177224179 Science and Education for Smart Growth Operational Programme Executive Agency
Funding ESF ==> Science and Education for Smart Growth
Date of the Contract/Order 18.12.2015
Start Date 18.12.2015
End Date 26.07.2019
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България

Description

Brief description
Осигуряване на финансирането на възнаграждения, осигурителни вноски и други дължими според действащото законодателство плащания, както и допълнителни възнаграждения и допълнително здравно осигуряване за служители, работещи в Управляващия орган на ОП НОИР.
Activities
  • Activity: Осигуряване на финансирането на възнаграждения, осигурителни вноски и други дължими според действащото законодателство плащания, както и допълнителни възнаграждения и допълнително здравно осигуряване за служители, работещи в Управляващия орган на ОП НОИР: Дейността ще осигури финансово брутното месечно възнаграждение на служителите от ИА ОП НОИР, изпълняващи функции по управление и изпълнение на ОП НОИР, на основание Кодекса на труда, Закона за държавния служител, Наредбата за структурата и организацията на работната заплата и Наредбата за заплатите на служителите в държавната администрация , относно определяне на видовете и минималните размери на допълнителните трудови възнаграждения, както и на реда и начина за определяне и изчисляване на трудовите възнаграждения на работниците и служителите на ИА ОП НОИР , включително всички дължими плащания към бюджета и допълнително здравно осигуряване., Contracted Amount: 11 068 398.00 , Reported Amount: 7 627 697.10

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Дял (в %) на сертифицираните разходи, спрямо верифицираните от УО, Measure Unit: %, Base Value: 0.00 , Target amount: 97.00 , Reached amount: 742.99
Indicator 2 Number of employees (FTEs) whose salaries are financed by Technical Assistance, Measure Unit: Еквивалент на пълно работно време, Base Value: 0.00 , Target amount: 96.00 , Reached amount: 393.00
Indicator 3 Share of the costs verified by the MA versus the costs reported by beneficiaries, Measure Unit: %, Base Value: 0.00 , Target amount: 89.00 , Reached amount: 383.25

Financial Information

Total Project cost 11 068 398.00 BGN
Grant 11 068 398.00 BGN
Self amount 0.00 BGN
Total actual amounts paid 7 260 946.82 BGN
Percentage of EU co-financing 85.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN