UMIS Number | BG05SFOP001-4.002-0001-C03 |
Project Name | Provision of funds for salaries of the Audit Authority under the European Structural and Investment Funds |
Beneficiary | 175618225 Audit of EU Funds' Executive Agency |
Funding | ESF ==> Good Governance |
Date of the Contract/Order | 26.02.2016 |
Start Date | 01.01.2016 |
End Date | 28.02.2019 |
Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
Location of Performance |
|
Brief description |
По този проект ще се финансират възнагражденията и осигурителни вноски върху тези възнаграждения за извършени дейности по ЕСИФ на изпълнителния директор и служителите от специализираната администрация. |
Activities | None |
Partners | None |
Contractors | None |
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Number of employees, whose remunerations are co-funded by technical assistance, Measure Unit: Number, Base Value: 0.00 , Target amount: 55.00 , Reached amount: 234.25 |
Indicator 2 | Annual turnover of the beneficiaries’ staff, Measure Unit: %, Base Value: 5.00 , Target amount: 5.00 , Reached amount: 0.00 |
Total Project cost | 9 060 636.72 BGN |
Grant | 9 060 636.72 BGN |
Self amount | 0.00 BGN |
Total actual amounts paid | 9 060 636.72 BGN |
Percentage of EU co-financing | 85.00 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
There are no tender procedures |
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN