| UMIS Number | BG06RDNP001-19.821-0002-C02 |
| Project Name | "Major repair of street No. 21 from point 35 to point 37, village Karageorgievo and mayor repair of a street in the town of Aytos (between Radi Borukov St. and Chudni Skali St. from point 52 to point 2053), Aytos Municipality" |
| Beneficiary | 000056764 AYTOS MUNICIPALITY |
| Funding | EZFRSR ==> Rural Development Programme |
| Date of the Contract/Order | 24.04.2025 |
| Start Date | 24.04.2025 |
| End Date | 15.09.2025 |
| Status of Implementation of the Contract/Order of the Grant | Contracted |
| Location of Performance |
|
| Brief description |
Настоящият проект има за цел подобряване на транспортно-експлоатационните характеристики на уличната настилка в град Айтос и село Карагеоргиево, община Айтос, като се повиши безопасността на автомобилното и пешеходното движение, както и комфорта при пътуване. Създаването и обновяването на техническата инфраструктура е основата за създаването на оптимална жизнена среда на селските райони. Чрез реализация на настоящия проект ще се засили социално-икономическото и културното развитие на общината. Проектът включва дейности по реконструкция на две улици от територията на община Айтос: улица № 21 от о.т.35 до о.т.37, с. Карагеоргиево и улица в гр. Айтос между ул. „Ради Боруков“ и ул. „Чудни скали“ от о.т.52 до о.т.2053. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Население, облагодетелствано от дребномащабните инвестиции, Measure Unit: Number, Base Value: 0.00 , Target amount: 18 418.00 , Reached amount: 18 334.00 |
| Total Project cost | 127 661.21 EUR |
| Grant | 127 661.21 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 124 291.26 EUR |
| Percentage of EU co-financing | 90.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Основен ремонт на улица № 21 от о.т.35 до о.т.37, с. Карагеоргиево и основен ремонт на улица в гр. Айтос (между ул. „Ради Боруков“ и ул. „Чудни скали“ от о.т.52 до о.т.2053), община Айтос:
Обособена позиция № 1: Основен ремонт на улица в гр. Айтос (между ул. „Ради Боруков“ и ул. „Чудни скали“ от о.т.52 до о.т.2053);
Обособена позиция № 2: Основен ремонт на улица № 21 от о.т.35 до о.т.37, с. Карагеоргиево;
,
Estimated Amount: 128 745.26
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN