UMIS Number | BG06RDNP001-19.134-0005-C03 |
Project Name | REPAIR AND RECONSTRUCTION of Voyvoda Gencho Kargov - 1920, Gurkovo, Municipality of Gurkovo |
Beneficiary | 000804291 NCH Voyvoda Gencho Kargov - 1920 " |
Funding | EZFRSR ==> Rural Development Programme |
Date of the Contract/Order | 26.08.2020 |
Start Date | 26.08.2020 |
End Date | 30.06.2025 |
Status of Implementation of the Contract/Order of the Grant | Contracted |
Location of Performance |
|
Brief description |
Реализацията на проекта ще допринесе до ограничаването на диспропорциите в териториалното разпределение на населението и обезлюдяването на селските райони. |
Activities |
|
Partners | None |
Contractors | None |
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Население, което се ползва от подобрената инфраструктура и публични услуги, Measure Unit: Number, Base Value: 284 350.91 , Target amount: 284 350.91 , Reached amount: 0.00 |
Indicator 2 | Създадени работни места, Measure Unit: Number, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00 |
Total Project cost | 268 636.20 BGN |
Grant | 268 636.20 BGN |
Self amount | 0.00 BGN |
Total actual amounts paid | 134 318.09 BGN |
Percentage of EU co-financing | 90.00 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
There are no tender procedures |
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN