| UMIS Number | BG05M2OP001-3.014-0004-C02 |
| Project Name | "DIRECTIONS - Interactions in the school community for full integration, equal access to quality education and successful future realization of students from small settlements" |
| Beneficiary | 000961718 Primary School "Sv. Sv.Kiril amp; Metodii”, Drazhevo village |
| Funding | ESF ==> Science and Education for Smart Growth 2014-2020 |
| Date of the Contract/Order | 07.05.2020 |
| Start Date | 07.05.2020 |
| End Date | 25.10.2022 |
| Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
| Location of Performance |
|
| Brief description |
Проектът „ПОСОКИ - Взаимодействия в училищната общност за пълноценно интегриране, равен достъп до качествено образование и успешна бъдеща реализация на ученици от малките населени места“ цели социално включване на деца и ученици от маргинализираните групи чрез подобряване на достъпа им до качествено образование, повишаване на качеството на училищното образование в 3 от малките населени места на община Тунджа и намаляване на броя на необхванатите от образователната система, на отпадащите от училище и на ранно/преждевременно напусналите училище ученици. За постигането на тези цели са планирани следните дейности: 1. Работилница за родителски умения - създаване на Родителски клубове 2. Реална и виртуална читанка 3. "Ти избираш своята бъдеща професия" 4. Работилница "Здраве от природата" 5. Работилница "Безопасност на движението по пътищата" 6. Лятна академия "Краезнание" 7. Подбор и назначаване на училищни сътрудници 8. Междуучилищен обмен: Успешни практики за подкрепа за социално включване на ученици от маргинализирани групи чрез подобряване на достъпа им до качествено образование. При осъществяването на дейностите ще се прилага интегриран подход с участието на всички членове на училищната общност – ученици, родители, педагогически специалисти. Като резултат проектът „ПОСОКИ - Взаимодействия в училищната общност за пълноценно интегриране, равен достъп до качествено образование и успешна бъдеща реализация на ученици от малките населени места“ ще надгради добрите практики в училищата по осъществяване на приоритетите в образователната система – равен достъп до качествено образование, насърчаване и повишаване на грамотността на учениците, мотивиране на учениците за занимания в STEM - направленията, целодневна организация на учебния ден, кариерно ориентиране, интеграцията на ученици от етническите малцинства. |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Children, students and youths from ethnic minorities (including Roma) integrated in the education system, Measure Unit: Number, Base Value: 0.00 , Target amount: 170.00 , Reached amount: 174.00 |
| Indicator 2 | Disadvantaged children, students and young people (incl. Roma), participating in activities for educational integration and re-integration, Measure Unit: Number, Base Value: 0.00 , Target amount: 170.00 , Reached amount: 195.00 |
| Total Project cost | 62 897.21 EUR |
| Grant | 62 897.21 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 62 897.20 EUR |
| Percentage of EU co-financing | 85.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - годишен абонамент за образователен софтуер,
Estimated Amount: 1 022.58
|
| Procedure 2 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - доставка на дидактически материали,
Estimated Amount: 2 163.08
|
| Procedure 3 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - доставка на канцеларски материали и офис консумативи,
Estimated Amount: 2 204.14
|
| Procedure 4 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - доставка на лаптопи, принтери и електронни книги,
Estimated Amount: 9 947.61
|
| Procedure 5 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - доставка на оборудване и обзавеждане,
Estimated Amount: 12 438.88
|
| Procedure 6 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - доставка на спортни пособия,
Estimated Amount: 2 061.36
|
| Procedure 7 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - доставка на учебна литература и пособия,
Estimated Amount: 472.94
|
| Procedure 8 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - доставка на храна (пакети суха храна) и кафе-паузи,
Estimated Amount: 383.47
|
| Procedure 9 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - извършване на външна услуга – транспорт на участниците по дейности,
Estimated Amount: 1 748.62
|
| Procedure 10 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - разходи за застраховки на участниците по дейности,
Estimated Amount: 199.66
|
| Procedure 11 |
Subject to due process: Директно възлагане по чл. 20, ал.4 от ЗОП - разходи за провеждане и участие в мероприятия ( хотелско настаняванe),
Estimated Amount: 4 669.80
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN