| UMIS Number | BG06RDNP001-19.134-0002-C03 |
| Project Name | Reconstruction and rehabilitation of streets and sidewalks in the Municipality of Maglij, Stara Zagora District, Object 3: Dabovo village: Section: Ninth September from 6 to 221 - left canvas with an approximate length of 610 m |
| Beneficiary | 000817867 Municipality of Maglizh |
| Funding | EZFRSR ==> Rural Development Programme |
| Date of the Contract/Order | 07.07.2020 |
| Start Date | 07.07.2020 |
| End Date | 30.06.2023 |
| Status of Implementation of the Contract/Order of the Grant | Contracted |
| Location of Performance |
|
| Brief description |
С изпълнението на проекта се цели повишаване привлекателността на града, качеството и комфорта на обитаване, чрез интегрирано въздействие върху значими градски пространства. За обект: Реконструкция и рехабилитация на улици и тротоари в Община Мъглиж, Област Стара Загора, Подобект 3: с. Дъбово: Участък: Улица "Девети Септември" от ОТ 6 до ОТ 221 - ляво платно с приблизителна дължина 610 м |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Население, което се ползва от подобрената инфраструктура и публични услуги, Measure Unit: Number, Base Value: 280 528.20 , Target amount: 280 528.20 , Reached amount: 0.00 |
| Indicator 2 | Създадени работни места, Measure Unit: Number, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00 |
| Total Project cost | 137 745.06 EUR |
| Grant | 137 745.06 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 137 745.05 EUR |
| Percentage of EU co-financing | 90.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Реконструкция и рехабилитация на улици и тротоари в с. Дъбово, община Мъглиж,
Estimated Amount: 137 930.29
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN