Identification

UMIS Number BG16RFOP002-6.002-0157-C01
Project Name Recovering SMEs by improving energy efficiency
Beneficiary 148084781 ARTVISION
Funding ERDF ==> Innovations and Competitiveness
Date of the Contract/Order 21.09.2022
Start Date 21.09.2022
End Date 04.07.2023
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Североизточен (BG33), Варна (BG331), Аксаково, гр.Аксаково

Description

Brief description
Възстановяване на МСП чрез подобряване на енергийната ефективност
Activities None

Participating Organizations

Partners None
Contractors
  • Contractor: SYSTEMS amp; TECHNOLOGIES, Contracted Amount*: 42 314.98 , Reported Amount**: 42 314.98
  • Contractor: EM STROI COMPLECT LTD, Contracted Amount*: 176 190.00 , Reported Amount**: 176 190.00
  • Contractor: T amp; S - consult grup, Contracted Amount*: 7 900.00 , Reported Amount**: 7 900.00
  • Contractor: KOSTOV KLIMA EOOD, Contracted Amount*: 62 400.00 , Reported Amount**: 62 400.00
  • Contractor: CSA CERT, Contracted Amount*: 9 900.00 , Reported Amount**: 9 900.00
Subcontractors
  • Subcontractor: TCS Uluslararasi Belgelendirme Hizmetleri San. Ve Tic. Ltd. Sti, Contracted Amount*: 0.00
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Number of enterprises receiving grants, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Number of enterprises receiving support, Measure Unit: предприятия, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 298 704.98 BGN
Grant 149 352.48 BGN
Self amount 149 352.50 BGN
Total actual amounts paid 149 352.48 BGN
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: „Доставка и монтаж на 3 бр. термопомпи за отопление и охлаждане въздух-вода и 1 бр. слънчева система за топла вода и битово горещо водоснабдяване“ , Estimated Amount: 62 500.00
Procedure 2 Subject to due process: Доставка и монтаж на следните енергоспестяващи осветители: 1. Камбани с мощност 100W – 4 бр. 2. Линейни осветителни тела с мощност 28W – 54 бр. 3. Линейни осветителни тела с мощност 36W – 37 бр. 4. Линейни осветителни тела с мощност 54W – 53 бр. , Estimated Amount: 42 316.00
Procedure 3 Subject to due process: Доставка и полагане на 300 м2 Топлоизолационна плоча от EPS и 930 м2 Топлоизолационни плочи от минерална вата., Estimated Amount: 176 200.00
Procedure 4 Subject to due process: Предоставяне на консултантски услуги за ВЪВЕЖДАНЕ на системи за енергиен мениджмънт в предприятията съгласно изискванията на стандарт БДС EN ISO 50001 (Energy Management Systems)/EN ISO 50001,, Estimated Amount: 8 000.00
Procedure 5 Subject to due process: Предоставяне на консултантски услуги за СЕРТИФИЦИРАНЕ на системи за енергиен мениджмънт в предприятията съгласно изискванията на стандарт БДС EN ISO 50001 (Energy Management Systems)/EN ISO 50001,, Estimated Amount: 10 000.00

Notes:

All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN