| UMIS Number | BG16RFOP002-2.077-1910-C01 |
| Project Name | Supporting medium-sized enterprises to overcome the economic impact of the COVID-19 pandemic |
| Beneficiary | 202853796 CASCADAS 16 EOOD |
| Funding | ERDF ==> Innovations and Competitiveness 2014-2020 |
| Date of the Contract/Order | 09.03.2021 |
| Start Date | 09.03.2021 |
| End Date | 13.01.2022 |
| Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
| Location of Performance |
|
| Brief description |
Подкрепа за средни предприятия за преодоляване на икономическите последствия от пандемията COVID-19 |
| Activities | None |
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| None |
| Total Project cost | 57 520.34 EUR |
| Grant | 57 520.34 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 57 520.34 EUR |
| Percentage of EU co-financing | 85.00 % |
|
|||||||||||||||
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|||||||||||||||
| Procedure 1 |
Subject to due process: Извършване на СМР, съгласно количествени сметки, включващи необходимите материали и труд за изпълнението им, по обособени позиции:
1. Изпълнение на настилки - полагане на шлайфан бетон, топлоизолация, циментова замазка и щампован бетон.
2. Доставка и монтаж на врати.
3. Доставка и монтаж на електрическо захранване на осветление и вентилация.
4. Обличане на въздуховоди с два слоя куфари от гипсокартон и полагане на вата.,
Estimated Amount: 84 416.85
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN