Identification

BG-RRP-4.032-0136-C01
Combined project TUTRAKAN for construction of new local electricity storage faciltiies ("BESS"), behind the meter, with an installed capacity of 1.4MW and capacity of 3MWh to a newly built and entered into exploitation photovoltaic power plant Tutrakan with nominal generation capacity of 4MW and nominal installed capacity of 3.6 MW AC
176789460 MINISTRY OF ENERGY
20.02.2025
20.02.2025
31.03.2026
In execution (starting date)
Location of Performance
  • Bulgaria, North and South East Bulgaria (BG3), North Central (BG32), Silistra (BG325), Tutrakan

Notes:

Elements in light blue allow detailed view when selected
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN
The project is financed by the Operational Programme "Technical Assistance" and co-financed by the European Union through the European Regional Development Fund.
In implementing the project № 0115-CCU-2.1 "Information system for management and monitoring of EU funds in 2014-2020 - UMIS 2020" (BG161PO002-2.1.01-0007-C0001).