Financial Information
10 203 202.66
EUR
7 186 915.84
EUR
3 016 286.82
EUR
3 928 519.10
EUR
85.00
%
Financial Corrections
| Reason | % of financial correction |
Financial corrections amounts1,2 | Contract | ||
|---|---|---|---|---|---|
| Grant | Self-financing | Total | |||
| Нарушения в документацията за обществени поръчки | 5.00 | 40 000.41 | 0.00 | 40 000.41 | BUILDING GROUP |
| Нарушения в документацията за обществени поръчки | 5.00 | 51 718.30 | 0.00 | 51 718.30 | VI-DEI-PLEVEN |
| Нарушения в документацията за обществени поръчки | 5.00 | 73 038.01 | 0.00 | 73 038.01 | BM-GROUP-ENGENERING |
| Нарушения в документацията за обществени поръчки | 25.00 | 237 928.59 | 0.00 | 237 928.59 | BM-GROUP-ENGENERING |
| Нарушения в документацията за обществени поръчки | 25.00 | 206 934.61 | 0.00 | 206 934.61 | VI-DEI-PLEVEN |
| Липса на добро финансово управление | 26 072.82 | 0.00 | 26 072.82 | VI-DEI-PLEVEN | |
| Нарушения в документацията за обществени поръчки | 5.00 | 2 772.60 | 538.54 | 3 311.14 | SI-Consult 2 |
| Нарушения в документацията за обществени поръчки | 5.00 | 127 760.03 | 85 173.35 | 212 933.38 | "PSG" |
| Нарушения в документацията за обществени поръчки | 0.00 | 0.00 | 0.00 | 0.00 | KA MOBIL |
| Нарушения в документацията за обществени поръчки | 10.00 | 3 971.41 | 0.00 | 3 971.41 | STEMO |
| Нарушения в документацията за обществени поръчки | 5.00 | 9 501.22 | 0.00 | 9 501.22 | OBEDINENIE "MON KONSULT 207 |
| Липса на добро финансово управление | 62 981.86 | 0.00 | 62 981.86 | Project-level financial correction | |
Notes:
* The amount of the actual amounts paid cumulative
1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.
2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.
Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN
1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.
2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.
Elements in light blue allow detailed view when selected
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN